Project Report - Brentwood High School & Community College, Sale Manchester

Titan security fencing was contact by the school facilities Manager Mike Colman.

Take down and removal of existing steel railings.

Take down and removal of existing steel railings.

Take down and removal of existing steel railings.

Take down and removal of existing steel railings.

Having attended site to carry out a survey the task was to take down and remove from site approximately 200 linear Mtrs of 2.4Mtr high solid round bar steel railings from the rear perimeter of the school play area and replace with 2.4 anti-climb mesh fencing.

There was one important factor that we had to allow for whilst assessing the work that needed to be carried out was this work had to be carried out within a two-week period due to the school being special needs and with a two-week holiday approaching the ball was rolling.

The school’s students could not be interrupted whilst we were on site therefore it was a must that this work had a deadline of two weeks completion whilst the school was on shut down.

Titan Security fencing provided a written quotation and a decision was made by the school to place a purchase order with Titan based on a number of factors, 

  • Brentwood High school carried out checks on Titan and was impressed that we are also an approved contractor for Greater Manchester Police.

  • Our site operatives and staff are all fully DBS cleared.

  • Health and safety’s paramount, all staff are CITB trained and we are CHAS accredited.

  • Having over 60 schools, colleges nurseries and academies on our books it is second nature for Titan to carry out work within the school environment.

  • We have a school code of conduct that our staff strictly follow.

Installation of new 358 mesh security fencing.

Installation of new 358 mesh security fencing.

Having provided all the relevant Risk Assessments and Method statements work commenced, Titan Security Fencing Limited took down and removed from site sections of the 2.4Mtr high steel railings at one time and replaced the said section with new 2.4Mtr high galvanised and powder coated to RAL 6005 green 358 anti-climb mesh fencing on RHS post firmly set into rapid setting concrete maintain security at all times.

Installation of new 358 mesh security fencing.

Installation of new 358 mesh security fencing.

Work was complete two days earlier than our agreed schedule including a full site clean prior to handover.

Our Contracts Director handing over the completed works to head of Finance.

Our Contracts Director handing over the completed works to head of Finance.

The school head, facilities and finance team were impressed how well our operatives carried out the contract, Mrs M Finny head of finance commented “we chose Titan Security Fencing due to their professional approach from the outset, having also noted that Titan carry out work for Greater Manchester Police basically says it all, we would highly recommend Titan to anyone requiring their services we are very please from start to completion”